Posted on December 10, 2016 at 12:16 pm by Clay Curtin
In October 2016, staff issued a
public bid request to hire a drilling contractor for the
Menlo Park Municipal Water District’s first
emergency water supply well at the City Corporation Yard located at 333 Burgess Drive. The well drilling phase will be less than 60 days and will include a continuous 24/7 drilling process spanning 7-10 days. Other non-drilling project construction activities will occur during normal working hours. Maggiora Bros. Drilling Inc., the city’s contractor, is anticipated to begin construction in January 2017. Staff will implement an extensive outreach program to notify nearby residents and businesses of the upcoming construction, which will include door hangers, postcards and community meetings. The well will be temporarily capped while the final design of the wellhead facilities is completed. Construction of the wellhead facilities will follow and is anticipated to occur in summer 2017.