Capital Improvement Program

City of Menlo Park
701 Laurel Street
Menlo Park, CA 94025

Tel. 650.330.6740
Fax 650.327.5497

Project Engineer
Randolph Craig

Consultant
Alta Planning & Design

 



Related Links
2007-08 Budget Report Page
Caltrain Bicycle Tunnel-FAQ

Caltrain Bike/Pedestrian Undercrossing Study and Conceptual Design

The purpose of this project is to significantly improve the safety for access of pedestrians and bicyclists across the Caltrain tracks between Ravenswood Avenue and San Francisquito Creek. This project will examine several potential locations where a tunnel could be constructed in the future. The final plan line for the project will be coordinated with the El Camino Real/Downtown Specific Plan and the potential High Speed Rail Alignment/Location.

This project is included in the City's General Plan and has been approved as a City Council Project Priority for fiscal year 2007-2008.

Subscribe to Caltrain Bike/Pedestrian Undercrossing Web Page updates


Past Activities
2009, May 27 City staff met with representatives of the potentially impacted property owners Office of Stanford Real Estate and Menlo Station Development to discuss future needs.
2009, April 13 Bicycle Commission - City staff had a follow up meeting with the Bicycle Commission to discuss potential crossing routes.  The Commission passed a motion recommending that a plan line be established with a direct connection between Middle Avenue and Burgess Park.
Bicycle Commission Minutes 4.13.09
2009, March 11 Transportation Commission - City staff provided a project update and presented two conceptual alternatives for the undercrossing.  The alternatives were prepared by Alta Planning and Design and can be viewed through the Transportation Program.
Conceptual Alternative 1  |  Conceptual Alternative 2

The Commission passed a motion to recommend to Council that a plan line be established at Middle Avenue that would connect to Burgess Drive.
Transportation Commission Minutes 3.11.09
2009, March 9 Bicycle Commission - City staff provided a project update and presented two conceptual alternatives for the undercrossing.  The alternatives were prepared by Alta Planning and Design and can be viewed through the Transportation Program.
Conceptual Alternative 1  |  Conceptual Alternative 2

The Commission passed a motion to have a follow-up discussion with additional City staff.
Bicycle Commission Minutes 3.9.09
2009, March 5 Community Meeting - City staff and Alta Planning and Design (consultant) held a meeting to give a project update and discuss the conceptual design alternatives with the intent of developing a consensus on the preferred conceptual design option.
Video
2008, Sep 10 The preferred location, as indicated by the general consensus of those in attendance of the previous public meetings, was presented to the Transportation Commission. The Commission voted to accept the location as presented by staff, namely the Middle Ave to Burgess Park alignment, for the bike/pedestrian tunnel. The motion passed with three votes yes, two votes no, and two abstentions.
Transportation Commission Minutes 09.10.08
2008, Sep 8 The preferred location, as indicated by the general consensus of those in attendance of the previous public meetings, was presented to the Bicycle Commission. After considering numerous factors, including feedback from community meetings and the consultant retained on the project, the proximity to desirable destinations, relative costs, projected usage by the community, convenience and accessibility, the Bicycle Commission unanimously recommends to the City Council that the bike/pedestrian underpass be located at Middle/Burgess.
Bicycle Commission Minutes 09.08.08
2008, Aug City staff meets with representatives of the potentially impacted property owners Office of Stanford Real Estate and Menlo-Station Development.
2008, Jul 31 A citywide meeting was held to discuss ideas, concerns, and possible locations for an undercrossing.
2008, Jun 26 A neighborhood meeting was held to discuss ideas, concerns, and possible locations for an undercrossing.
Presentation
2008, May 20 The City Council authorizes the City Manager to enter into an agreement in the amount of $40,968 with Alta Planning and Design to develop a Caltrain bicycle/pedestrian undercrossing location and plan line.
Staff Report  |  Summary of Actions  |  Meeting Minutes


The preferred undercrossing location identified in two public meetings and supported by both the Bicycle and Transportation Commissions is shown in red below.