This project consists of constructing a new synthetic turf soccer field, rubber track, tennis courts, basketball court, parking lot, restrooms and landscaping.




Conceptual Plan for Improvements to Kelly Park.

Planned Activities
2011, Jun 21 Kelly Park is currently open, please visit Community Services Department for more information.

Past Activities
2011, Jun 11 Grand Opening    
2010, Jun 22 Award of contract to OC Jones & Sons for construction of project.
Staff Report  |

2009, Jan 27 City Council approves "Conceptual Plan D" for Kelly Park Improvement Project & amends the contract with Callander Associates for the development of construction documents and determines that the citywide sports field study is complete.
Staff Report  |

2008, Jul 16 Conceptual plan alternatives for Burgess Park improvements will be presented to the community and the Parks and Recreation Commission. The Commission will meet at 6:00 p.m. in the Burgess Recreation Center. Plan details are available using the links below.
Staff Report  |  Conceptual Plan Alternatives  |  Detailed Cost Estimates
2008, Sep 23 The City Council will be presented with a recommendation to consider the conceptual plans identified as the preferred alternatives for future improvements at Burgess Park and Kelly Park by the Parks and Recreation Commission.
2008, Jun 18 A new conceptual plan for improvements at Kelly Park is presented to the community and the Parks and Recreation Commission. The new plan, "Plan D," is based on comments received at the Commission's February meeting as well as discussions with representatives of the Alpine/West Menlo Little League and the non-profit organization EPATT.

The features of Plan D include a multi-purpose, artificial turf field that can accommodate an adult sized soccer field, a football field, and a lacrosse field. The field can also be used for softball and baseball; however, a permanent backstop, pitcher's mound, or base setup will not be included.

Other features of the plan include a rubberized running track around the perimeter of the field, bleacher seating that overlooks the track and field, two new tennis courts, and one multi-use court that can be used for basketball or tennis. Also included are new lighting fixtures, new restrooms, and additional parking.

The total estimated cost for the plan is $4.4 million, which includes the costs of environmental study, final design, construction, and maintenance equipment.

The Commission voted unanimously to approve the plan for recommendation to Council.
Staff Report  |  Meeting Minutes
2008, Feb 27 Three conceptual plans for Kelly Park are presented to the community and the Parks and Recreation Commission at the Commission's monthly meeting.
Plan A  |  Plan B  |  Plan C
2008, Jan 12 City staff conducts a focus group meeting to identify user needs and potential concerns of neighbors as a basis for developing conceptual plans for Kelly Park. Design elements that were identified as desirable include: an adult sized soccer field, an adult sized softball field, track and field components, a perimeter path, and no significant reduction in parking spaces.
2007, Nov 27 The City Council authorizes a contract with Callander Associates to conduct the Playing Fields Study along with the Citywide Sports Field Study.
Staff Report